# The Electricity (Exemption from the Requirement for a Generation Licence) (England and Wales) Order 2002, Article 4: Conditions on exemptions


(1) The exemption granted by article 3(1) to Powergen CHP is subject to compliance with the conditions specified in paragraph (2) below.
(2) (a) Powergen CHP is not a licensed generator.
(b) The Stoke generating station is connected to the total system and is not normally capable of exporting more electrical power than 100 megawatts to the total system, disregarding power temporarily provided in excess of 100 megawatts due to technical circumstances outside the reasonable control of Powergen CHP.
(3) The exemption granted by article 3(2) to Powergen Cogeneration is subject to compliance with the conditions specified in paragraph (4) below.
(4) (a) Powergen Cogeneration is not a licensed generator.
(b) The Castleford generating station is connected to the total system and is not normally capable of exporting more electrical power than 100 megawatts to the total system, disregarding power temporarily provided in excess of 100 megawatts due to technical circumstances outside the reasonable control of Powergen Cogeneration.

---
Source: https://www.legislation.gov.uk/uksi/2002/823/article/4 (the official version)
Page: https://openlegislation.uk/electricity-exemption-from-the-requirement-for-a-generation-licence-england-and-wales-order-2002/article-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.