OpenLegislation

Article 4 Conditions on exemption

Original text. Later amendments are not shown.

The exemption granted by article 3 to Barrow Offshore Wind is subject to compliance with the conditions specified in sub paragraphs (a) and (b) below—

(a)

Barrow Offshore Wind is not a licensed generator;

(b)

the Barrow generating station is connected to the total system and is not normally capable of exporting more electrical power than 100 megawatts to the total system, disregarding power temporarily provided in excess of 100 megawatts due to technical circumstances outside the reasonable control of Barrow Offshore Wind.