Article 5 Conditions on exemption
The exemption granted by article 3(b) to Millennium Wind Energy Limited is subject to compliance with the following conditions—
(a)
that Millennium Wind Energy Limited does not hold a licence under section 6(1)(a) of the Act;
(b)
that Millennium Wind Farm is connected to the total system in Scotland; and
(c)
that, except in circumstances outside the reasonable control of Millennium Wind Energy Limited, Millennium Wind Farm does not export more than 100 megawatts of electrical power to the total system in Scotland.