Article 5 Conditions on exemption
(1)
The exemption granted by article 3 to Cambrian Wind Energy is subject to compliance with the conditions specified in paragraph (2) below.
(2)
(a)
Cambrian Wind Energy is not a licensed generator.
(b)
the Cefn Croes generating station is connected to the total system and is not normally capable of exporting more electrical power than 100 megawatts to the total system, disregarding power temporarily provided in excess of 100 megawatts due to technical circumstances outside the reasonable control of Cambrian Wind Energy.