Article 4 Conditions on exemptions
(1)
The exemption granted by article 3 to Braes of Doune Limited is subject to compliance with the following conditions—
(a)
Braes of Doune Limited is not a licensed generator; and
(b)
The Braes of Doune generating station is connected to a distribution system in Scotland operated by a licensed distributor and is not normally capable of exporting more electrical power than 100 megawatts to that system, disregarding power temporarily provided in excess of 100 megawatts due to technical circumstances outside the reasonable control of Braes of Doune Limited.