OpenLegislation

Article 4 Conditions on exemption

Original text. Later amendments are not shown.

The exemption granted by article 3(1) to FWL is subject to compliance with the conditions specified in sub-paragraphs (a) and (b)—

(a)

FWL is not a licensed generator;

(b)

the Farr generating station is connected to the total system in Great Britain and is not normally capable of exporting more electrical power than 100 megawatts to that system, disregarding power temporarily provided in excess of 100 megawatts due to technical circumstances outside the reasonable control of FWL.