OpenLegislation

Paragraph 8

Original text. Later amendments are not shown.

The exemption granted by article 3(1) to Snowdonia Pumped Hydro Limited in respect of Glyn Rhonwy Pumped Hydro is subject to the conditions that—

(a)

Glyn Rhonwy Pumped Hydro is connected to the total system;

(b)

except in circumstances outside the reasonable control of Snowdonia Pumped Hydro Limited, Glyn Rhonwy Pumped Hydro does not export more than 100 megawatts of electrical power to the total system; and

(c)

Snowdonia Pumped Hydro Limited does not hold a licence under section 6(1)(a) of the Act.