# The Electricity (Individual Exemption from the Requirement for a Generation Licence) (Riverside Energy Park) (England) Order 2025, Article 2: Exemption from prohibition of unlicensed generation of electricity for supply

Extent: E+W+S

(1) Exemption is granted from section 4(1)(a) of the Act (prohibition of unlicensed generation of electricity for supply) to Riverside Energy Park Limited in respect of Riverside 2.
(2) The exemption in paragraph (1) is granted indefinitely.
(3) The exemption granted by paragraph (1) is subject to the following conditions—
(a) Riverside 2 is connected to the total system;
(b) Riverside 2 does not export more than 100 megawatts of electrical power to the total system, except in circumstances outside the reasonable control of Riverside Energy Park Limited; and
(c) Riverside Energy Park Limited does not hold a licence under section 6(1)(a) of the Act in relation to Riverside 2.
(4) In this article—
“the Act” means the Electricity Act 1989;
“Riverside 2” means the energy from waste facility which is located in Belvedere, London, England, whose entrance is situated at Ordnance Survey map reference TQ 495 806;
“Riverside Energy Park Limited” means the company of that name registered in England and Wales with company number 11536739;
“the total system” means all transmission systems and distribution systems, located in Great Britain, of holders of licences under section 6(1)(b) and (c) of the Act.

---
Source: https://www.legislation.gov.uk/uksi/2025/1001/article/2 (the official version)