The exemption granted by article 3(b) of this Order is subject to compliance with the following conditions—
(a) Ferrybridge Multifuel 2 Generating Station is connected to the total system in England and Wales;
(b) Ferrybridge Multifuel 2 Generating Station does not export more than 100 megawatts of electrical power to the total system in England and Wales, except in circumstances outside the reasonable control of Ferrybridge MFE 2 Limited; and
(c) Ferrybridge MFE 2 Limited is not a licensed generator.

---
Source: https://www.legislation.gov.uk/uksi/2018/967/article/5 (the official version)