# The Electricity (Individual Exemptions from the Requirement for a Generation Licence) Order 2019, Article 5: Conditions on exemptions


The exemption granted by article 3(b) of this Order is subject to compliance with the following conditions—
(a) Clocaenog Forest Wind Farm is connected to the total system;
(b) Clocaenog Forest Wind Farm does not export more than 100 megawatts of electrical power to the total system, except in circumstances outside the reasonable control of Innogy Renewables UK Limited; and
(c) Innogy Renewables UK Limited is not a licensed generator in respect of Clocaenog Forest Wind Farm.

---
Source: https://www.legislation.gov.uk/uksi/2019/930/article/5 (the official version)