# The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019, Paragraph 102

Extent: E+W+S

(1) Article 157 is amended as follows.
(2) In paragraph 2—
(a) omit points (a) to (c), (h) and (i);
(b) in point (j), for the second sentence, substitute—
“The sharing agreement for the GB synchronous area shall require that the positive reserve capacity on FRR and the risk of non-delivery due to sharing shall be assessed continually by the TSOs of the LFC block.”;
(c) in point (k), for the second sentence, substitute—
“The sharing agreement shall require that the negative reserve capacity on FRR and the risk of non-delivery due to sharing shall be assessed continually by the TSOs of the LFC block.”.

---
Source: https://www.legislation.gov.uk/uksi/2019/533/schedule/1/paragraph/102 (the official version)
Page: https://openlegislation.uk/electricity-network-codes-and-guidelines-system-operation-and-connection-amendment-etc-eu-exit-regulations-2019/schedule-1/paragraph-102
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.