(1) Article 187 is amended as follows.
(2) In paragraphs 1, 2 and 3—
(a) for “each synchronous area” substitute “ the GB synchronous area ” in each place that it occurs;
(b) for “notify” substitute “ publish ” in each place that it occurs;
(c) omit “to ENTSO for Electricity for publication” in each place that it occurs.

---