Article 3 Requirement to make arrangements etc.

Original text. Later amendments are not shown.

Each public electricity supplier in England and Wales (whose names are specified in the left-hand column of the Table in Schedule 1 (specified aggregate amounts of non-fossil fuel generating capacity) to this Order) shall, before 30th September 1990, make (in so far as he has not already done so) and produce to the Director evidence showing that he has made such additional arrangements as will secure that, for each period shown in that Table, the aggregate amount of non-fossil fuel generating capacity available to him from relevant non-fossil fuel generating stations will not be less than that specified in the Table in relation to him for that period.