Schedule 1 SPECIFIED AGGREGATE AMOUNTS OF NON-FOSSIL FUEL GENERATING CAPACITY
| (1) | (2) | (3) |
|---|---|---|
| Name of supplier | Periods | Aggregate amounts of non-fossil fuel generating capacity |
1 London Electricity plc | (a) 1 April 1990 to 31 March 1992 | (a) 855.300 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 846.300 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 821.800 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 785.800 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 738.800 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 813.900 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 771.900 MW | |
2 SEEBOARD plc | (a) 1 April 1990 to 31 March 1992 | (a) 709.899 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 702.429 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 682.094 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 652.214 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 613.204 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 675.537 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 640.677 MW | |
3 Southern Electric plc | (a) 1 April 1990 to 31 March 1992 | (a) 1060.572 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 1049.412 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 1019.032 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 974.392 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 916.112 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 1009.236 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 957.156 MW | |
4 South Western Electricity plc | (a) 1 April 1990 to 31 March 1992 | (a) 487.521 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 482.391 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 468.426 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 447.906 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 421.116 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 463.923 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 439.983 MW | |
5 Eastern Electricity plc | (a) 1 April 1990 to 31 March 1992 | (a) 1171.761 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 1159.431 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 1125.866 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 1076.546 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 1012.156 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 1115.043 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 1057.503 MW | |
6 East Midlands Electricity plc | (a) 1 April 1990 to 31 March 1992 | (a) 769.770 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 761.670 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 739.620 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 707.220 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 664.920 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 732.510 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 694.710 MW | |
7 Midlands Electricity plc | (a) 1 April 1990 to 31 March 1992 | (a) 829.641 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 820.911 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 797.146 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 762.226 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 716.636 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 789.483 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 748.743 MW | |
8 South Wales Electricity plc | (a) 1 April 1990 to 31 March 1992 | (a) 299.355 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 296.205 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 287.630 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 275.030 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 258.580 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 284.865 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 270.165 MW | |
9 Manweb plc | (a) 1 April 1990 to 31 March 1992 | (a) 496.074 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 490.854 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 476.644 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 455.764 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 428.504 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 472.062 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 447.702 MW | |
10 Yorkshire Electricity Group plc | (a) 1 April 1990 to 31 March 1992 | (a) 701.346 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 693.966 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 673.876 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 644.356 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 605.816 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 667.398 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 632.958 MW | |
11 Northern Electric plc | (a) 1 April 1990 to 31 March 1992 | (a) 453.309 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 448.539 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 435.554 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 416.474 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 391.564 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 431.367 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 409.107 MW | |
12 NORWEB plc | (a) 1 April 1990 to 31 March 1992 | (a) 718.452 MW |
(b) 1 April 1992 to 30 September 1992 | (b) 710.892 MW | |
(c) 1 October 1992 to 31 March 1995 | (c) 690.312 MW | |
(d) 1 April 1995 to 30 April 1995 | (d) 660.072 MW | |
(e) 1 May 1995 to 31 March 1996 | (e) 620.592 MW | |
(f) 1 April 1996 to 30 June 1996 | (f) 683.676 MW | |
(g) 1 July 1996 to 31 March 1998 | (g) 648.396 MW |