OpenLegislation

Article 2 Requirement to make arrangements etc.

Original text. Later amendments are not shown.

Each public electricity supplier in England and Wales shall, before 20th November 1991, make (in so far as he has not already done so) and produce to the Director evidence showing that he has made such additional arrangements as will secure that for each period shown in Tables A to F in Schedule 1 (specified aggregate amounts of generating capacity) to this Order the aggregate amount of generating capacity available to him from non-fossil fuel generating stations of the description specified in the heading to each particular Table will not be less than the amount specified in that Table in relation to him for that period.