Schedule 2 CONDITIONS PRECEDENT

Original text. Later amendments are not shown.

The requirements referred to in article 3(1)(a) of this Order are

(1)

that planning permission and all necessary consents (including any necessary wayleave consents), easements and rights to enable any relevant non-fossil fuel generating station to be constructed and operated in accordance with and as contemplated by the terms of the relevant arrangements have been granted;

(2)

that planning permission and all necessary consents (including any necessary wayleave consents), easements and rights to enable any public electricity supplier in whose authorised area any relevant non-fossil fuel generating station is to be located to comply with his obligations as contemplated by the terms of the relevant arrangements have been granted;

(3)

that the operator has entered into, and there has come into force, a connection agreement;

(4)

that the operator holds a licence or has the benefit of an exemption under Part I of the Act authorising him to generate electricity and to convey electricity from the place at which it is generated to the point of delivery for the purposes of the relevant arrangements;

(5)

(to the extent that the arrangements relate to a relevant non-fossil fuel generating station whose operator is so required) that the operator has become a party to the pooling and settlement agreement;

(6)

that the commissioning process has been satisfactorily completed.