Paragraph 1
Table A below relates to hydro generating stations–
Table A
| Name of Supplier | Period | ||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | |
| Eastern Electricity plc | 0.000 | 0.000 | 0.204 | 0.448 | 0.920 | 1.134 | 1.214 | 1.214 | 1.214 | 1.214 | 1.214 | 1.214 | 1.214 | 1.214 | 1.214 | 1.214 | 1.009 | 0.394 | 0.169 | 0.078 | 0.000 |
| East Midlands Electricity plc | 0.000 | 0.000 | 0.134 | 0.294 | 0.604 | 0.745 | 0797 | 0.797 | 0.797 | 0.797 | 0.797 | 0.797 | 0.797 | 0.797 | 0.797 | 0.797 | 0.662 | 0.259 | 0.111 | 0.051 | 0.000 |
| London Electricity plc | 0.000 | 0.000 | 0.149 | 0.327 | 0.672 | 0.828 | 0.886 | 0.886 | 0.886 | 0.886 | 0.886 | 0.886 | 0.886 | 0.886 | 0.886 | 0.886 | 0.736 | 0.288 | 0.123 | 0.057 | 0.000 |
| Manweb plc | 0.000 | 0.000 | 0.086 | 0.189 | 0.389 | 0.480 | 0.513 | 0.513 | 0.513 | 0.513 | 0.513 | 0.513 | 0.513 | 0.513 | 0.513 | 0.513 | 0.426 | 0.166 | 0.071 | 0.033 | 0.000 |
| Midlands Electricity plc | 0.000 | 0.000 | 0.144 | 0.317 | 0.651 | 0.803 | 0.859 | 0.859 | 0.859 | 0.859 | 0.859 | 0.859 | 0.859 | 0.859 | 0.859 | 0.859 | 0.714 | 0.279 | 0.119 | 0.055 | 0.000 |
| Northern Electric plc | 0.000 | 0.000 | 0.078 | 0.173 | 0.355 | 0.438 | 0.469 | 0.469 | 0.469 | 0.469 | 0.469 | 0.469 | 0.469 | 0.469 | 0.469 | 0.469 | 0.390 | 0.152 | 0.065 | 0.030 | 0.000 |
| NORWEB plc | 0.000 | 0.000 | 0.125 | 0.275 | 0.564 | 0.695 | 0.744 | 0.744 | 0.744 | 0.744 | 0.744 | 0.744 | 0.744 | 0.744 | 0.744 | 0.744 | 0.618 | 0.241 | 0.103 | 0.048 | 0.000 |
| SEEBOARD plc | 0.000 | 0.000 | 0.123 | 0.271 | 0.557 | 0.687 | 0.735 | 0.735 | 0.735 | 0.735 | 0.735 | 0.735 | 0.735 | 0.735 | 0.735 | 0.735 | 0.611 | 0.238 | 0.102 | 0.047 | 0.000 |
| Southern Electric plc | 0.000 | 0.000 | 0.184 | 0.406 | 0.833 | 1.026 | 1.098 | 1.098 | 1.098 | 1.098 | 1.098 | 1.098 | 1.098 | 1.098 | 1.098 | 1.098 | 0.913 | 0.357 | 0.153 | 0.071 | 0.000 |
| South Wales Electricity plc | 0.000 | 0.000 | 0.051 | 0.114 | 0.234 | 0.289 | 0.309 | 0.309 | 0.309 | 0.309 | 0.309 | 0.309 | 0.309 | 0.309 | 0.309 | 0.309 | 0.257 | 0.100 | 0.042 | 0.019 | 0.000 |
| South Western Electricity plc | 0.000 | 0.000 | 0.084 | 0.186 | 0.382 | 0.471 | 0.504 | 0.504 | 0.504 | 0.504 | 0.504 | 0.504 | 0.504 | 0.504 | 0.504 | 0.504 | 0.419 | 0.163 | 0.070 | 0.032 | 0.000 |
| Yorkshire Electricity Group plc | 0.000 | 0.000 | 0.122 | 0.268 | 0.550 | 0.678 | 0.726 | 0.726 | 0.726 | 0.726 | 0.726 | 0.726 | 0.726 | 0.726 | 0.726 | 0.726 | 0.603 | 0.236 | 0.101 | 0.047 | 0.000 |
In Table A–
period 1 means 1 December 1998 to 31 March 1999
-
period 2 means 1 April 1999 to 31 March 2000
-
period 3 means 1 April 2000 to 31 March 2001
-
period 4 means 1 April 2001 to 31 March 2002
-
period 5 means 1 April 2002 to 31 March 2003
-
period 6 means 1 April 2003 to 31 March 2004
-
period 7 means 1 April 2004 to 31 March 2005
-
period 8 means 1 April 2005 to 31 March 2006
-
period 9 means 1 April 2006 to 31 March 2014
-
period 10 means 1 April 2007 to 31 March 2008
-
period 11 means 1 April 2008 to 31 March 2009
-
period 12 means 1 April 2009 to 31 March 2010
-
period 13 means 1 April 2010 to 31 March 2011
-
period 14 means 1 April 2011 to 31 March 2012
-
period 15 means 1 April 2012 to 31 March 2013
-
period 16 means 1 April 2013 to 31 March 2014
-
period 17 means 1 April 2014 to 31 March 2015
-
period 18 means 1 April 2015 to 31 March 2016
-
period 19 means 1 April 2016 to 31 March 2017
-
period 20 means 1 April 2017 to 31 March 2018
-
period 21 means 1 April 2018 to 31 November 2018
capacity amounts are expressed in megawatts.