Regulation 3 Interpretation

Original text. Later amendments are not shown.

In these Regulations—

  • “application” means an application under section 36 of the Electricity Act 1989 for a consent to construct, extend or operate an offshore generating station, together with any application under section 36A of that Actf1 for a declaration relating to rights of navigation which is made with the application under section 36;

  • “harbour” and “harbour authority” have the same meaning as in section 57 of the Harbours Act 1964f2;

  • “offshore generating station” means a generating station that is, or is to be, located—

    1. (a)

      within the Renewable Energy Zone; or

    2. (b)

      within waters in or adjacent to England and Wales which are between the mean low water mark and the seaward limits of the territorial sea;

  • “Renewable Energy Zone” means so much of the area designated by the Renewable Energy Zone (Designation of Area) Order 2004f3 as does not include the area designated by the Renewable Energy Zone (Designation of Area) (Scottish Ministers) Order 2005f4 as an area in relation to which the Scottish Ministers are to have functions; and

  • “Wales” has the same meaning as in section 155 of the Government of Wales Act 1998f5.

Annotations

Footnotes

f1

Section 36A was inserted into the Electricity Act 1989 by section 99(1) of the Energy Act 2004.

f2

1964 c. 40.

f3

S.I. 2004/2668. This Order, made under section 84 of the Energy Act 2004, designated a Renewable Energy Zone covering waters whose co-ordinates are specified in the Schedule to the Merchant Shipping (Prevention of Pollution) (Limits) Regulations 1996 (S.I. 1996/2128), as amended by the Merchant Shipping (Prevention of Pollution) (Limits) Regulations 1997 (S.I. 1997/506).

f4

S.I. 2005/3153.

f5

1998 c. 38.