Regulation 9 Fees payable on applications for consent
The fee to be paid to the Secretary of State upon an application being made shall be as specified in the Table below.
Table
| Subject matter of application for consent | Fee |
|---|---|
1 Construction of an offshore generating station of megawatt capacity— | |
(a) not exceeding 200 | £5000.00 |
(b) exceeding 200 but not exceeding 500 | £12000.00 |
(c) exceeding 500 | £20000.00 |
2 Construction and operation of an offshore generating station of megawatt capacity— | |
(a) not exceeding 200 | £5000.00 |
(b) exceeding 200 but not exceeding 500 | £12000.00 |
(c) exceeding 500 | £20000.00 |
3 Operation of an offshore generating station of megawatt capacity— | |
(a) not exceeding 200 | £5000.00 |
(b) exceeding 200 but not exceeding 500 | £12000.00 |
(c) exceeding 500 | £20000.00 |
4 Extension of an offshore generating station | £1000.00 |
5 Extension and operation of an offshore generating station of megawatt capacity— | |
(a) not exceeding 200 | £5000.00 |
(b) exceeding 200 but not exceeding 500 | £12000.00 |
(c) exceeding 500 | £20000.00 |