# The Electricity (Offshore Generating Stations) (Applications for Consent) (Wales) Regulations 2019, Regulation 2: Interpretation

Extent: E+W

(1) In these Regulations—
“the 1990 Act” (“Deddf 1990”) means the Town and Country Planning Act 1990 ;
“application” (“cais”) means an application to the Welsh Ministers for consent under section 36 to construct, extend or operate a generating station , together with any application under section 36A for a declaration relating to rights of navigation which is made with the application under section 36;
“infrastructure consent development” (“datblygiad cydsyniad seilwaith”) means any development in respect of which an applicant is applying for consent in accordance with the provisions of the Infrastructure (Wales) Act 2024;
“local planning authority” (“awdurdod cynllunio lleol”) has the same meaning as in Part 1 of the 1990 Act;
“relevant planning authority” (“awdurdod cynllunio perthnasol”) means in relation to land in Wales, a local planning authority;
“section 90 development” (“datblygiad adran 90”) means any development in respect of which an applicant on making an application requests the Welsh Ministers to give a direction under section 90(2) or (2ZA) of the 1990 Act (deemed planning permission for development with government authorisation).
(2) Unless otherwise stated, any reference in these Regulations to a numbered section is a reference to that section of the Electricity Act 1989.

---
Source: https://www.legislation.gov.uk/wsi/2019/295/regulation/2 (the official version)
Page: https://openlegislation.uk/electricity-offshore-generating-stations-applications-for-consent-wales-regulations-2019/regulation-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.