An application must be in writing and must describe by reference to a map the place to which the application relates, that is, the place where—
(a) it is proposed to construct the generating station, where the proposed extension will be or where the station proposed to be operated is situated; ...
(b) any section 90 development will be situated ; and
(c) any infrastructure consent development will be situated.

---