# The Electricity Safety, Quality and Continuity Regulations 2002, Paragraph 7


Network details—
(a) voltage;
(b) equipment at site of event, whether overhead lines, underground cables, distributing mains, or service lines, or if other, specify;
(c) where relevant, whether the earthing of the low voltage network is by means of protective multiple earthing;
(d) extent of operation of circuit protection;
(e) in respect of events involving overhead lines—
(i) height of the electric line at point of contact, if any;
(ii) whether or not the electric line remained live on the ground or at a reduced height; and
(iii) whether or not the electric line was surrounded by insulation; and
(f) in respect of events not involving overhead lines—
(i) whether the equipment was situated indoors;
(ii) where a substation is involved, a brief description of substation physical security equipment, e.g. brick building, steel doors, nature of fencing; and
(iii) whether any security fence was also the perimeter fence.

---
Source: https://www.legislation.gov.uk/uksi/2002/2665/schedule/3/part/I/paragraph/7 (the official version)
Page: https://openlegislation.uk/electricity-safety-quality-and-continuity-regulations-2002/schedule-3/part-I/paragraph-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.