# The Electricity (Standards of Performance) Regulations 2005, Part I: Prescribed periods and prescribed sums applicable to all relevant operators


(1)
(2)
(3)
(4)
Regulation
Prescribed period
Prescribed sum domestic customer
Prescribed sum non-domestic customer
5(2)(a)
18 hours
£50
£100
5(2)(b)
£25
£25
6(4)(a)
24 hours
£25
£25
6(4)(b)
£25
£25
6(5)(a)
48 hours
£25
£25
6(5)(b)
£25
£25
6(6)(a)
£25
£25
6(6)(b)
£25
£25
7(2)(a)
18 hours
£50
£100
7(2)(b)
£25
£25
9(4)
£50
£50
10(3)
three hours on a working day
£20
£20
10(3)
four hours on any other day
£20
£20
11(2)
five working days
£40
£40
11(3)
15 workding days
£40
£40
12(4)
two days
£20
£20
12(5)
five days
£20
£20
12(6)
two days
£20
£20
13(2)
seven working days
£20
£20
13(4)(a)
£20
£20
13(4)(b)
five working days
£20
£20
14(2)(a)
five working days
£20
£20
14(2)(b)
five working days
£20
£20
14(2)(c)
five working days
£20
£20
15(2)
seven working days
£20
£20
15(4)(a)
£20
£20
15(4)(b)
five working days
£20
£20
16(3)
three hours on a working day
£20
£20
16(3)
four hours on any other day
£20
£20
17(2)
£20
£20
17(3)
£20
£20
19(4)
10 working days
£20
£20
19(5)
10 working days
£20
£20
19(6)
10 working days
£20
£20

---
Source: https://www.legislation.gov.uk/uksi/2005/1019/schedule/1/part/I (the official version)
Page: https://openlegislation.uk/electricity-standards-of-performance-regulations-2005/schedule-1/part-I
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.