# The Electricity (Standards of Performance) Regulations 2010 (revoked)

S.I. 2010/698 · made 8 March 2010 · revised to 1 April 2015

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

PDFs: Printed copy https://openlegislation.uk/electricity-standards-of-performance-regulations-2010-revoked/pdf/uksi_20100698_en.pdf

## Introductory text

Electricity
Made 8th March 2010
Coming into force 1st April 2010
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## Part I: General

## 1 Citation, commencement and transitional provisions

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 2 Revocation

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 3 General interpretation

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## Part II: Supply restoration standards of performance for electricity distributors

## 4 Interpretation of the normal and severe weather restoration standards

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 5 Supply restoration: normal conditions

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 6 Supply restoration: normal conditions – 5,000 or more customers' premises interrupted

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 7 Supply restoration: severe weather conditions

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 8 Supply restoration: rota disconnection

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 9 Supply restoration: Highlands and Islands

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 10 Exemptions from the normal and severe weather restoration standards

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 11 Supply restoration: multiple interruptions

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## Part III: Other individual standards of performance for electricity distributors

## 12 Distributor's fuse

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 13 Estimate of charges for connection

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 14 Notice of supply interruption

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 15 Voltage complaint

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## Part IV: Individual standards of performance for relevant suppliers

## 16 Charges and payments

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## Part V: Individual standards of performance for electricity suppliers

## 17 Meter disputes

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 18 Pre-payment meters

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## Part VI: Common obligations

## 19 Appointments

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 20 Disputes

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 21 Payments

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 22 Exemptions

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 23 Timing of notification

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 24 Notice of rights

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## Part VII: Overall standards of performance

## 25 Information to be given to customers about overall performance

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## Signature

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## Schedule 1: Data for the Purpose of Calculating Payments

## I Prescribed periods and prescribed sums applicable to all relevant operators

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## Schedule 2: Standards of Performance – Practice and Procedure for Determinations

### Part: Determination of disputes

## 1 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Timetable for the determination of individual disputes

## 2 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Procedure for the determination of individual disputes

## 3 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Determination of multiple disputes

## 4 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Timetable for determination of multiple disputes

## 5 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Procedure for the determination of multiple disputes

## 6 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Written statements

## 7 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Production of documents and other evidence

## 8 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Oral hearings

## 9 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Customer representatives for multiple disputes

## 10 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Collection of information in multiple disputes

## 11 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Payment to customers

## 12 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Set–off

## 13 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

### Part: Costs

## 14 

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

## Explanatory note

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

---
Source: https://www.legislation.gov.uk/uksi/2010/698 (the official version)