# The Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2000, Schedule 1: DESCRIPTIONS OF DEVELOPMENT FOR THE PURPOSES OF THE DEFINITION OF “ SCHEDULE 1 DEVELOPMENT”


The carrying out of development to provide either of the following—
(1) a generating station, the construction of which (or the operation of which) will require a section 36 consent and which is either (a) a nuclear generating station or (b) a non-nuclear generating station with a heat output of 300 megawatts or more; or
(2) an electric line installed above ground with (a) a voltage of 220 kilovolts or more and (b) a length of more than 15 kilometres, the installation of which (or the keeping installed of which) will require a section 37 consent.

---
Source: https://www.legislation.gov.uk/uksi/2000/1927/schedule/1 (the official version)
Page: https://openlegislation.uk/electricity-works-environmental-impact-assessment-england-and-wales-regulations-2000/schedule-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.