# The Electricity Works (Environmental Impact Assessment) (England and Wales) Regulations 2017, Regulation 28: Application website

Extent: E+W

(1) The developer or, where paragraph (2) applies, the relevant authority must ensure that a copy of each item set out in an entry in column 1 of the table is able to be accessed by the public at a website (the “application website”) free of charge from the date set out in the corresponding entry in column 2 until the date on which the application is determined.
(1) Item
(2) Date from which item must be accessible at application website
Notice published under regulation 22
The date on which the first notice is published under regulation 22(4)
EIA report
The date on which the first notice is published under regulation 22(4)
Notice published under regulation 26
The date on which the first notice is published under regulation 26(2)
Further environmental information
The date on which the first notice is published under regulation 26(2)
Additional environmental information
As soon as reasonably practicable after the date on which the additional environmental information is received by the developer or, where paragraph (2) applies, the relevant authority
(2) This paragraph applies where the relevant authority notifies the developer in writing that the relevant authority will comply with the obligations in paragraph (1).
(3) Where the relevant authority notifies the developer under regulation 5(2A) of the Electricity Generating Stations (Variation of Consents) (England and Wales) Regulations 2013 , or in a case where the Welsh Ministers are the relevant authority, under regulation 5(3) of the Electricity (Offshore Generating Stations) (Variation of Consents) (Wales) Regulations 2019, that the relevant authority will, instead of the developer, comply with the obligations in paragraph (2) of that regulation to publish material on a website, the relevant authority must also notify the developer under paragraph (2) of this regulation that the relevant authority will comply with the obligations in paragraph (1) of this regulation.
(4) The application website must be the same website on which information is published under regulation 5(2) of the Electricity Generating Stations (Variation of Consents) (England and Wales) Regulations 2013, or in a case where the Welsh Ministers are the relevant authority, under regulation 5(2) of the Electricity (Offshore Generating Stations) (Variation of Consents) (Wales) Regulations 2019.

---
Source: https://www.legislation.gov.uk/uksi/2017/580/regulation/28 (the official version)