# The Electricity Works (Environmental Impact Assessment) (Scotland) Regulations 2017, Paragraph 1: Descriptions of development


The carrying out of development to provide any of the following—
(1) nuclear generating station or other nuclear reactors (except research installation for the production and conversion of fissionable and fertile materials, whose maximum power does not exceed 1 kilowatt continuous thermal load);
(2) thermal generating station with a heat output of 300 megawatts or more; or
(3) construction of overhead electrical power lines with a voltage of 220 kilovolts or more and a length of more than 15 kilometres.

---