# Energy Act 2023, Paragraph 14

Extent: E+W+S

In paragraph 12, for “operational purposes” substitute “construction, commissioning or operational purposes” in each of the following places—
(a) sub-paragraphs (1) to (3);
(b) sub-paragraph (10);
(c) sub-paragraph (11) (in both places).

---
Source: https://www.legislation.gov.uk/ukpga/2023/52/schedule/15/paragraph/14 (the official version)
Page: https://openlegislation.uk/energy-act-2023/schedule-15/paragraph-14
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.