Article 3 Modification of the minimum rate of compensation water discharged from the Holme Styes Reservoir into the River Ribble
While this Order is in force—
(a)
conditions 4.1 and 4.2(ii) of the Schedule of Conditions to the Licence are to be read as if for the words “1.98 megalitres”, there were substituted the words “0.99 megalitres”; and
(b)
condition 4.2(i) of the Schedule of Conditions to the Licence is to be read as if for the words “4 megalitres” there were substituted the words “0.99 megalitres”.