# The Environmental Impact Assessment (Agriculture) Regulations (Northern Ireland) 2007, Paragraph 5

Extent: N.I.

(1) If—
(a) a project which is subject to a further decision has commenced; and
(b) it appears to the Department to be necessary to safeguard the integrity of the European site or Area of Special Scientific Interest,
the Department may by notice require the person responsible for carrying out such works, or the owner/occupier of the relevant land, to carry out such works of reinstatement as may be reasonable in the circumstances,
(2) A notice under paragraph (1) must state the period during which the works must be carried out.
(3) Any person who carries out such reinstatement works is entitled, on making a claim in accordance with paragraph 8, to recover from the Department compensation in respect of any expenses reasonably incurred by him in carrying out those works.

---
Source: https://www.legislation.gov.uk/nisr/2007/421/schedule/4/paragraph/5 (the official version)
Page: https://openlegislation.uk/environmental-impact-assessment-agriculture-regulations-northern-ireland-2007/schedule-4/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.