Division 4.3 How to notify
United Kingdom
A company should notify by filling in the form presented in Annex I and submitting it without delay to the relevant competent authority(ies). The operator notifying must provide the information required in the form. However, no company should delay a notification because part of the information is not yet available.
It may be helpful to divide the form into two parts. The first part should be filled in immediately (Sections 1 to 5) and the second part (Section 6) should be filled in when the information has been collected (a timetable for providing the missing information should be transmitted) and then when there is a serious risk situation or when the producer/distributor opts to submit the notification only to the authority of the Member State in which they are established. Notification should not be delayed when some of the fields in a section cannot be completed.
The GPSD requires that the competent authorities be informed immediately. A company must therefore inform them without delay, as soon as the relevant information has became available, and in any case within 10 daysf1 since it has reportable information, even while investigations are continuing, indicating the existence of a dangerous product. When there is a serious risk companies are required to inform the authority(ies) immediately and in no case later than three days after they have obtained notifiable information.
In an emergency situation, such as when immediate action is taken by a company, the company should inform the authorities immediately and by the fastest means.
Annotations
Footnotes
- f1
-
All deadlines mentioned in the text are expressed in calendar days.