Total corrections — Budget item 6701

MSMeasureFYReasonType%CurrencyAmountDeductions already madeFinancial impact
BEFinancial audit — Late payments2005Failure to meet payment deadlinesone-offEUR-45 406,3-45 406,30,0
Total BE EUR -45 406,3-45 406,30,0
DEExceptional market measures2001Weaknesses in documentation and physical on-the-spot supervisionsflat-rate5 %EUR-1 182 038,830,0-1 182 038,83
DEExceptional market measures2002Weaknesses in documentation and physical on-the-spot supervisionsflat-rate5 %EUR-284 869,30,0-284 869,3
DEDirect Payments2005Poor follow-up of evident overclaims identified following GIS establishmentone-offEUR-32 236,960,0-32 236,96
Total DE EUR -1 499 145,090,0-1 499 145,09
DKClearance of accounts2005Financial clearanceone-offDKK-96 741,7-23 951,9-72 789,8
DKFinancial audit — Overshooting2005Overshooting of financial ceilingsone-offEUR-125 996,55-125 996,550,0
Total DK DKK -96 741,7-23 951,9-72 789,8
Total DK EUR -125 996,55-125 996,550,0
ESMilk quota1997Milk deliveries underdeclaredone-offEUR-1 350 020,320,0-1 350 020,32
ESArable Crops2004The sanctions and exclusion due to intentional non-compliance foreseen for in Article 33 of Commission Regulation (EC) No 2419/2001 are not appliedflat-rate2 %EUR-276 716,910,0-276 716,91
ESArable Crops2005The sanctions and exclusion due to intentional non-compliance foreseen for in Article 33 of Regulation (EC) No 2419/2001 are not appliedflat-rate2 %EUR-274 130,080,0-274 130,08
ESFruit and Veg's — Citrus Processing1998Reimbursement following partial annulment of Decision 2004/136/EC by the judgement of the Court of Justice in case T-220/04one-offEUR532 684,560,0532 684,56
ESFruit and Veg's — Citrus Processing1999Reimbursement following partial annulment of Decision 2004/136/EC by the judgement of the Court of Justice in case T-220/04one-offEUR435 837,70,0435 837,7
ESFruit and Veg's — Citrus Processing2000Reimbursement following partial annulment of Commission Decision 2004/136/EC by the judgement of the Court of Justice in case T-220/04one-offEUR11 032,220,011 032,22
ESMeat Premiums — Bovines2002Systematic late controls on the spotflat-rate5 %EUR-30 407,710,0-30 407,71
ESMeat Premiums — Bovines2003Systematic late controls on the spotflat-rate5 %EUR-159 064,730,0-159 064,73
ESMeat Premiums — Bovines2004Systematic late controls on the spotflat-rate5 %EUR-232 483,160,0-232 483,16
ESPublic Storage of butter2002Undue financing costsone-offEUR-141 002,610,0-141 002,61
ESPublic Storage of butter2003Undue financing costsone-offEUR-67 250,220,0-67 250,22
Total ES EUR -1 551 521,260,0-1 551 521,26
FRFinancial audit — Late payments2005Failure to meet payment deadlinesone-offEUR-696 062,71-934 532,21238 469,5
FRFinancial audit — Overshooting2005Overshooting of financial ceilingsone-offEUR-501,92-501,920,0
FRFruit and Veg's — Producer organisations2003Non-respect of recognition criteriaone-offEUR-24 478 123,670,0-24 478 123,67
FRFruit and Veg's — Producer organisations2004Non-respect of recognition criteriaone-offEUR-25 243 299,770,0-25 243 299,77
FRMeat Premiums — Bovines2003Weaknesses regarding controls of animals only identified by tattoosflat-rate2 %EUR-168 812,00,0-168 812,0
FRMeat Premiums — Bovines2004Weaknesses regarding controls of animals only identified by tattoosflat-rate2 %EUR-115 584,00,0-115 584,0
FRMeat Premiums — Bovines2005Weaknesses regarding controls of animals only identified by tattoosflat-rate2 %EUR-65 764,00,0-65 764,0
Total FR EUR -50 768 148,07-935 034,13-49 833 113,94
GBFinancial audit — Overshooting2005Overshooting of financial ceilingsone-offEUR-795 921,450,0-795 921,45
Total GB EUR -795 921,450,0-795 921,45
ITDried Fodder2002Non-adequate control of the enterprises transforming the fodderflat-rate5 %EUR-1 828 877,580,0-1 828 877,58
ITDried Fodder2003Non-adequate control of the enterprises transforming the fodderflat-rate2 %EUR-44 421,460,0-44 421,46
ITDried Fodder2003Non-adequate control of the enterprises transforming the fodderflat-rate5 %EUR-2 399 395,340,0-2 399 395,34
ITDried Fodder2004Weaknesses regarding controls of operators of the networkflat-rate2 %EUR-512 153,030,0-512 153,03
ITDried Fodder2004Weaknesses regarding controls of operators of the networkflat-rate5 %EUR-9 132,020,0-9 132,02
ITDried Fodder2004Non-adequate control of the enterprises transforming the fodderflat-rate5 %EUR-645 442,920,0-645 442,92
ITDried Fodder2005Weaknesses regarding controls of operators of the networkflat-rate2 %EUR-774 140,650,0-774 140,65
ITDried Fodder2005Weaknesses regarding controls of operators of the networkflat-rate5 %EUR-1 552,690,0-1 552,69
ITMeat Premiums — Bovines2003Systematic late controls on the spotflat-rate5 %EUR-456 327,00,0-456 327,0
ITMeat Premiums — Bovines2004Systematic late controls on the spotflat-rate5 %EUR-295 911,00,0-295 911,0
ITOlive Oil — Production aid2001Shortcomings in controls of the mills, weaknesses in respect of the olive trees and the yieldflat-rate5 %EUR-40 284 269,550,0-40 284 269,55
ITOlive Oil — Production aid2002Shortcomings in controls of the mills, weaknesses in respect of the olive trees and the yieldflat-rate5 %EUR-34 743 757,290,0-34 743 757,29
ITOlive Oil — Production aid2003Shortcomings in controls of the mills, weaknesses in respect of the olive trees and the yieldflat-rate5 %EUR-113 946,890,0-113 946,89
ITOlive Oil — Production aid2004Shortcomings in controls of the mills, weaknesses in respect of the olive trees and the yieldflat-rate5 %EUR-1 289 091,840,0-1 289 091,84
Total IT EUR -83 398 419,260,0-83 398 419,26
NLFinancial audit — Late payments2005Failure to meet payment deadlinesone-offEUR-206 100,68-206 100,680,0
NLFinancial audit — Overshooting2005Overshooting of financial ceilingsone-offEUR-60 859,36-60 859,360,0
Total NL EUR -266 960,04-266 960,040,0
PTWine — Restructuring2001Weaknesses in key on-the-spot controls and in determination of the eligible areasflat-rate2 %EUR-77 342,020,0-77 342,02
PTWine — Restructuring2002Weaknesses in key on-the-spot controls and in determination of the eligible areasflat-rate2 %EUR-649 828,570,0-649 828,57
PTWine — Restructuring2003Weaknesses in key on-the-spot controls and in determination of the eligible areasflat-rate2 %EUR-673 890,890,0-673 890,89
PTWine — Restructuring2004Weaknesses in key on-the-spot controls and in determination of the eligible areasflat-rate2 %EUR-565 733,930,0-565 733,93
Total PT EUR -1 966 795,410,0-1 966 795,41
SEArable Crops2004The level of on-the-spot (Rapid Field Visits) checks carried out under the minimum rate requiredflat-rate5 %SEK-12 198 084,10,0-12 198 084,1
SEDirect Payments2005The level of on-the-spot (Rapid Field Visits) checks carried out under the minimum rate requiredflat-rate5 %SEK-12 640 336,050,0-12 640 336,05
SEDirect Payments2005Low quality of the remote sensing checksflat-rate2 %SEK-9 280 142,640,0-9 280 142,64
Total SE SEK -34 118 562,790,0-34 118 562,79

Total corrections — Budget item 05 07 01 07

MSMeasureFYReasonType%CurrencyAmountDeductions already madeFinancial impact
GRFinancial audit — Overshooting2005Overshooting of financial ceilingsone-offEUR0,0-348 181,42348 181,42
Total GR EUR 0,0-348 181,42348 181,42
IEFinancial audit — Late payments2005Failure to meet payment deadlinesone-offEUR-1 064 668,75-3 495 598,232 430 929,48
Total IE EUR -1 064 668,75-3 495 598,232 430 929,48