Article 29a Implementation of actionsF1
United Kingdom
Participants shall implement actions in compliance with all the conditions and obligations set out in this Decision, Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council f1 and Commission Delegated Regulation (EU) No 1268/2012 f2 , as well as in the call for proposals and the grant agreement.
Participants shall make no commitments which are incompatible with this Decision or the grant agreement. Where a participant fails to comply with its obligations regarding the technical implementation of the action, the other participants shall comply with the obligations without any additional Union funding unless the Commission expressly relieves them of any of those obligations. Participants shall ensure that the Commission is informed in due time of any event which might significantly affect the implementation of the action or the interests of the Union.
Participants shall implement the action and shall take all necessary and reasonable measures to that end. They shall have the appropriate resources, as and when needed for carrying out the action. Where it is necessary for the implementation of the action, they may call upon third parties, including subcontractors, to carry out work under the action. Participants shall retain responsibility towards the Commission and towards the other participants for the work carried out.
The award of subcontracts for carrying out certain elements of the action shall be limited to the cases provided for in the grant agreement and to duly justified cases that could not be clearly foreseen at the time of entry into force of the grant agreement.
Third parties other than subcontractors may carry out work under the action under the conditions laid down in the grant agreement. The third party and the work to be carried out by it shall be identified in the grant agreement.
Costs incurred by those third parties may be deemed eligible if the third party meets all the following conditions:
it would be eligible for funding if it were a participant;
it is an affiliated entity or has a legal link to a participant implying a collaboration not limited to the action;
it is identified in the grant agreement; and
it abides by the rules applicable to the participant under the grant agreement with regard to eligibility of costs and control of expenditure.
Participants shall comply with national legislation, regulations and ethical rules in the countries where the action is carried out. Where appropriate, participants shall seek the approval of the relevant national or local ethics committees prior to the start of the action.
Annotations
Textual amendments
Footnotes
- f1
-
Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council of 25 October 2012 on the financial rules applicable to the general budget of the Union and repealing Council Regulation (EC, Euratom) No 1605/2002 ( OJ L 298, 26.10.2012, p. 1 );
- f2
-
Commission Delegated Regulation (EU) No 1268/2012 of 29 October 2012 on the rules of application of Regulation (EU, Euratom) No 966/2012 of the European Parliament and of the Council on the financial rules applicable to the general budget of the Union ( OJ L 362, 31.12.2012, p. 1 ).