  "url": "https://openlegislation.uk/eu-decision-2009-523/introduction",
  "json_url": "https://openlegislation.uk/eu-decision-2009-523/introduction.json",
  "legislation": "eudn/2009/523",
  "legislation_title": "Commission Decision of 10 December 2008 on State aid C 52/06 (ex NN 73/06, ex N 340/06) partially implemented by Poland for Odlewnia Żeliwa ‘Śrem’ S.A. (notified under document number C(2008) 7049) (Only the Polish text is authentic) (Text with EEA relevance) (2009/523/EC)",
  "legislation_url": "https://openlegislation.uk/eu-decision-2009-523",
  "path": "introduction",
  "kind": "introduction",
  "number": null,
  "heading": "Introductory text",
  "text": "Commission Decision\nof 10 December 2008\non State aid C 52/06 (ex NN 73/06, ex N 340/06) partially implemented by Poland for Odlewnia Żeliwa ‘Śrem’ S.A.\n(notified under document number C(2008) 7049)\n(Only the Polish text is authentic)\n(Text with EEA relevance)\n(2009/523/EC)\nTHE COMMISSION OF THE EUROPEAN COMMUNITIES,\nHaving regard to the Treaty establishing the European Community, and in particular the first subparagraph of Article 88(2) thereof,\nHaving regard to the Agreement on the European Economic Area, and in particular Article 62(1)(a) thereof,\nHaving called on interested parties to submit their comments pursuant to the provisions cited above,\nWhereas:\nI.\nPROCEDURE\n(1)\nOn 1 June 2006 the Polish authorities notified restructuring aid for Odlewnia Żeliwa ‘Śrem’ (hereinafter Odlewnia Śrem) mostly in the form of arrangements for public law liabilities to be paid in instalments. It was found that some of the aid measures had been granted after accession without the Commission’s approval. Hence they were deemed to be illegal aid.\n(2)\nBy letter of 6 December 2006, the Commission informed Poland that it had decided to initiate the procedure laid down in Article 88(2) of the EC Treaty in respect of the measures.\n(3)\nThe Commission’s decision to initiate the proceedings under Article 88(2) of the EC Treaty was published in the Official Journal of the European Union. The Commission invited interested parties to submit their comments on the proposed aid.\n(4)\nOn 31 January 2007 the Polish authorities submitted their comments on the opening of the investigation procedure. No comments were received from third parties.\n(5)\nOn 15 April 2008 the Commission sent a request for further information to the Polish authorities.\n(6)\nOn 30 April 2008 the Polish authorities replied, informing the Commission of the withdrawal of the planned measures. However, the Commission could not accept this as a withdrawal under Article 8 of Council Regulation (EC) No 659/99, as the debt payment deferrals already implemented had in fact had an effect on the beneficiary, giving it a clear advantage over other companies that paid their public law liabilities on time.\nII.\nDESCRIPTION OF THE BENEFICIARY AND THE RESTRUCTURING\nBeneficiary\n(7)\nOdlewnia Śrem started production in 1968. It produces mainly cast iron for the shipbuilding industry. Privatisation of the company began in 1999, when the State Treasury sold 85 % of its shares to CENTROZAP (44,9 %), BANK PEKAO (25,1 %) and employees (15 %). One of the reasons why the beneficiary’s situation deteriorated was the difficult financial situation of the main shareholder, CENTROZAP, which at one point held 71,4 % of Odlewnia Śrem’s shares. Currently Odlewnia Śrem is owned by PIOMA-ODLEWNIA, which holds 85,1 % of the shares. According to the Polish authorities, Odlewnia Śrem has a 6-8 % share of the Polish cast iron market. It is based in a region eligible for regional aid under Article 87(3)(a) of the EC Treaty.\nNational procedure\n(8)\nThe process of restructuring Odlewnia Śrem started in 2003. In 2004 the first restructuring programme was drawn up, and was approved by the President of the Agency for Industrial Development (ARP).\n(9)\nAccording to the Polish authorities the company wanted to take advantage of the opportunity created by amendments to the Act of 30 October 2002 on State aid for enterprises of special significance for the labour market which expanded the scope for writing off public law liabilities (Chapter 5a), but imposed additional requirements on the company, such as identifying part of its assets for transfer to an independent Operator. The Operator had to be a company wholly owned by ARP or the State Treasury. The proceeds from the sale of these assets by the Operator were to cover at least part of the public law liabilities of the company being restructured, and the remainder were to be written off when restructuring was completed. On 19 March 2006 the deadline for completing the restructuring procedure under Chapter 5a of the Act of 19 March 2006 expired, without the sale of assets by the Operator having taken place. Despite this, the President of ARP, in a decision dated 27 June 2006, declared that the restructuring had been completed as Odlewnia Śrem had recovered its viability and all that was now needed for full completion of the restructuring was the Commission’s consent to the arrangement allowing the company to pay its public law liabilities in instalments. Following the unsatisfactory termination of the Chapter 5a procedure, the company contacted its five public creditors to ask them to defer the payment deadlines for its liabilities on the basis of the more generally applicable provisions of tax law, which was less advantageous for them than the arrangement provided for in Chapter 5a.\nThe restructuring\n(10)\nAccording to the Polish authorities, the restructuring costs amount to PLN 43,6 million. The financial restructuring costs make up about 75 % of the total restructuring costs, the remainder being mainly expenditure relating to modernisation of the company’s infrastructure.\n(11)\nThe restructuring plan focuses, firstly, on modernisation of the production site and investments in improving the quality of the company’s administration (e.g. by introducing the SAP R/3 computer system as Odlewnia Śrem’s main IT tool).\n(12)\nSecondly, a large part of the restructuring consists in financial restructuring, i.e. mainly arrangements for payment in instalments and write-offs of public law liabilities. A partial write-off of civil law liabilities in the amount of PLN 1,4 million was also agreed under a composition agreement with creditors signed on 17 May 2005.\n(13)\nThirdly, in 2005 the company decreased the number of its employees to 1 457, down from 1 776 in 2002, and did not plan further employment restructuring. However, Poland submitted that the temporary suspension of the application of the Company Collective Bargaining Agreement constituted a reduction of employment costs as the company was temporarily not paying contributions to the Company Social Benefits Fund.\n(14)\nThe restructuring of assets consisted in the lease of assets not related to production such as a hotel (Ośrodek Wypoczynkowy in Ostrowieczno) and other facilities for a total price of PLN 0,4 million. The sale of further assets worth approximately PLN 2,6 million is also planned but has not yet been finalised.\n(15)\nBefore the Commission initiated the procedure laid down in Article 88(2) of the EC Treaty, it had been informed that the company had been trying to find a new investor since 2003 and the Polish authorities had been stressing the importance of privatisation for the company’s long-term viability. Poland has informed the Commission that this goal has been achieved as 85,1 % of Odlewnia Śrem’s shares have been sold to the private company PIOMA-ODLEWNIA.\n(16)\nOdlewnia Śrem has reduced its production capacity from 57 000 to 55 000 tonnes of cast iron per year and does not envisage a further reduction, claiming that this would put the company’s viability at risk. Poland has proposed two alternative compensatory measures. Firstly, the company has reduced its production of cast iron for industrial fittings by 50 % (from approximately 11 000 tones to 5 500 tonnes). Secondly, Poland states that the company will no longer be producing cast iron for wind power stations.\nIII.\nDECISION TO INITIATE THE PROCEDURE UNDER ARTICLE 88(2) OF THE EC TREATY\n(17)\nThe Commission decided to initiate the formal investigation procedure because it had doubts as to whether the restructuring aid was compatible with the common market. The doubts were based on four factors.\n(18)\nFirstly, the Commission had doubts as to whether Odlewnia Śrem could be considered a ‘firm in difficulty’ within the meaning of the Community Guidelines on State aid for rescuing and restructuring firms in difficulty (hereinafter 2004 Guidelines) and thus be eligible for restructuring aid, as Odlewnia Śrem showed a net profit of PLN 3,9 million in 2005.\n(19)\nSecondly, the Commission had doubts about whether the restructuring plan was capable of restoring the long-term viability of the beneficiary, since it seemed to focus on debt servicing and covering operating costs and the company seemed to be struggling to find a private investor.\n(20)\nThirdly, the Commission had doubts as to whether the aid was limited to the minimum necessary and whether the own contribution was significant and as high as possible, particularly since the Polish authorities had not provided any concrete privatisation plans, under which the own contribution would have been significantly greater.\n(21)\nFinally, the Commission had doubts about the compensatory measures, since Poland had not shown that the decreases in production referred to in recital 16 were indeed compensatory measures and not merely the result of external factors such as a decline in demand or the company’s inability to compete on the relevant markets.\nIV.\nPARTIES’ COMMENTS\n(22)\nThe Commission has received comments only from Poland.\nPolish authorities’ comments\nChanges in the State aid measures\n(23)\nThe Polish authorities have informed the Commission of some changes in the aid granted after accession, which should now be PLN 24,2 million. The table below summarises the state restructuring aid (aid already implemented and aid planned) to Odlewnia Śrem as notified by the Polish authorities in their comments on the initiation of the investigation procedure.\n(24)\nThe total nominal value of the State aid is PLN 43,6 million. These measures comprise a State guarantee, a loan granted on preferential terms, direct grants and deferrals and write-offs of public law liabilities. A detailed description of the State aid measures is presented in the table below (aid elements as indicated by the Polish authorities).\nTable 1\nState aid already granted\nA\nB\nC\nD\nE\nF\nNo\nPresumed date of agreement or decision\nGranting authority\nForm of aid\nNominal value(PLN)\nAid amount(PLN)\nState aid granted before accession and not applicable after accession\n1\n19.3.2004\nMayor of Śrem\nWrite-off of real estate tax liabilities (incl. interest) for the period 1.3.2002 — 30.6.2002\n738 748,02\n738 748,02\n2\n19.3.2004\nMayor of Śrem\nWrite-off of tax liabilities\n500 000,0\n500 000,0\n3\n23.4.2004\nARP\nLoan\n4 000 000,0\n4 000 000,0\n4\n28.4.2004\nARP\nCredit guarantee\n14 000 000,0\n14 000 000,0\n5\n30.4.2004\nMayor of Śrem\nWrite-off of interest on tax liabilities\n200 353,9\n200 353,9\nTotal\n19 439 101,92\n19 439 101,92\nState aid granted after accession\n6\n20.5.2004\nMinistry of Science and Information Technology\nGrant\n435 000,0\n352 350,0\n7\n9.5.2005\nZUS (Social Insurance Institution)\nSocial security contributions to be paid in instalments (incl. interest)\n5 385 415,31\n134 585,81\n8\n17.10.2005\nProvincial authority\nDeferral of payment\n855 438,78\n105 369,44\n9\n2nd quarter 2007\nProvincial authority\nEnvironmental charges due up to 30.6.2003 to be paid in instalments\n1 272 657,45\n247 003,92\n10\n2nd quarter 2007\nProvincial authority\nInterest on environmental charges to be paid in instalments (concerns item above)\n692 185,03\n126 365,78\n11\n2nd quarter 2007\nProvincial authority\nEnvironmental charges due up to 30.6.2003 to be paid in instalments\n422 946,34\n51 018,68\n12\n2nd quarter 2007\nProvincial authority\nInterest on environmental charges to be paid in instalments (concerns item above)\n274 950,1\n33 167,04\n13\n2nd quarter 2007\nState Fund for the Rehabilitation of the Disabled. (PFRON)\nState Fund for the Rehabilitation of the Disabled (PFRON) contributions due up to 30.6.2003 to be paid in instalments\n803 221,5\n148 274,11\n14\n2nd quarter 2007\nState Fund for the Rehabilitation of the Disabled. (PFRON)\nWrite-off of interest on contributions to the State Fund for the Rehabilitation of the Disabled (PFRON) due up to 30.6.2003\n421 085,2\n421 085,2\n15\n2nd quarter 2007\nState Fund for the Rehabilitation of the Disabled. (PFRON)\nState Fund for the Rehabilitation of the Disabled (PFRON) contributions for the period July 2003 — January 2004 to be paid in 20 quarterly instalments\n479 156,6\n155 721,64\n16\n2nd quarter 2007\nState Fund for the Rehabilitation of the Disabled. (PFRON)\nWrite-off of interest on contributions to the State Fund for the Rehabilitation of the Disabled (PFRON) for the period July 2003 — January 2004\n38 392,87\n38 392,87\n17\n2nd quarter 2007\nDistrict authority\nPayments for perpetual usufruct due up to 30.6.2003 to be paid in instalments\n263 496,0\n34 701,67\n18\n2nd quarter 2007\nDistrict authority\nWrite-off of interest on payments for perpetual usufruct due up to 30.6.2003 (concerns item above)\n137 890,0\n18 159,78\n19\n2nd quarter 2007\nZUS\nSocial security contributions due up to 30.6.2003 to be paid in instalments\n4 077 498,51\n46 619,38\n20\n2nd quarter 2007\nZUS\nInterest on social security contributions due up to 30.6.2003 to be paid in instalments (concerns item above)\n2 306 780,0\n26 341,18\n21\n2nd quarter 2007\nZUS\nContributions to the Labour Fund and Employee Benefits Guarantee Fund due up to 30.6.2003 to be paid in instalments\n1 275 873,09\n28 618,42\n22\n2nd quarter 2007\nZUS\nInterest on contributions to the Labour Fund and Employee Benefits Guarantee Fund due up to 30.6.2003 to be paid in instalments (concerns item above)\n727 023,0\n16 296,744\n23\n2nd quarter 2007\nZUS\nSocial security contributions due up to 30.6.2003 to be paid in instalments\n2 085 480,55\n29 309,94\n24\n2nd quarter 2007\nZUS\nInterest on social security contributions due up to 30.6.2003 to be paid in instalments (concerns item above)\n1 100 260,0\n15 463,36\n25\n2nd quarter 2007\nZUS\nWrite-off of enforcement costs related to late payment of social security contributions due up to 30.6.2003\n641 593,8\n641 593,8\n26\n2nd quarter 2007\nNational Fund for Environmental Protection and Water Management (NFOSiGW)\nGrant\n470 000,0\n470 000,0\nState aid granted after accession\n24 166 344,12\n3 140 438,76\nTotal State aid granted and planned\n43 605 446,04\n22 579 540,68\nOther issues raised by Poland in its comments on the opening of the investigation procedure\n(25)\nFirstly, as regards the company’s viability, the Polish authorities claimed that the restructuring had proved successful, as Odlewnia Śrem had managed to find a private strategic investor, which would bring in the capital needed and enable the company to regain credibility on the market.\n(26)\nPoland also stressed that the company had diversified its production, focusing on more sophisticated products with greater value added. The shift to the production of iron castings weighing over 300 kg proved to be a good move, as a number of competitors ceased production in this segment of the market and thus provided an opening for Odlewnia Śrem to become active in it.\n(27)\nThe Polish authorities confirmed that the company no longer had liquidity problems and that all its current business liabilities were being repaid on time.\n(28)\nSecondly, Poland argued that Odlewnia Śrem could be considered a ‘firm in difficulty’ within the meaning of the 2004 Guidelines, and thus be eligible for restructuring aid. The Polish authorities confirmed that the restructuring period started in 2003, when the company was clearly in difficulty. The fact that Odlewnia Śrem made a net profit of PLN 3,9 million in 2005 should be considered a sign that it recovered viability through the restructuring process.\n(29)\nThirdly, Poland provided further information about the company’s own contribution towards the overall cost of restructuring.\n(30)\nAccording to the Polish authorities, the beneficiary made a significant own contribution. The restructuring costs totalled PLN 43,6 million, while the sources of financing for restructuring which can be classified as an own contribution to the restructuring can be valued at PLN 23,7 million, made up of the capital brought in by the private investor (PLN 16 million), the revenue from the sale or lease of assets already carried out (PLN 0,4 million) and the temporary suspension of the application of the Company Collective Bargaining Agreement (PLN 7,3 million). As regards the last of these, the Polish authorities argue that it constitutes a reduction of the cost of employment benefits as Odlewnia Śrem is temporarily released from paying contributions to the Company Social Benefits Fund. This Fund was set up by Odlewnia Śrem and its trade unions voluntarily, and is not required by law. There are therefore no state resources involved. It has been explained that the decision was taken with the agreement of the trade unions, which agreed to sacrifice part of the employees’ benefits to support the restructuring. Therefore, the measure can be considered an own contribution.\n(31)\nIn addition, Poland reiterated its view that the following also constituted own contributions to restructuring costs:\na write-off and an arrangement for payment in instalments of civil law liabilities of PLN 2 million under a composition agreement signed with Odlewnia Śrem’s creditors;\ntrade credits granted by suppliers allowing Odlewnia Śrem a longer period than usual in which to pay for materials and services, which Poland calculates to be worth PLN 2,5 million;\nreceivables from clients evaluated at PLN 9 million (realised by imposing shorter payment periods on clients).\n(32)\nFinally, with regard to the requirement to limit distortion of competition, the Polish authorities cite the 50 % reduction in the company’s production of cast iron for industrial fittings (from approximately 11 000 tones to 5 500 tonnes). The fact that the company has ceased production of cast iron for wind power stations should be considered a valid compensatory measure.\n(33)\nPoland argues that demand for both types of product has been increasing in recent years and this trend is expected to continue. Poland has also stressed that Odlewnia Śrem has the technical capacity to produce as much as it did before restructuring, but it has undertaken to limit its output of cast iron for industrial fittings and completely cease production of cast iron for wind power stations. Hence, according to the Polish authorities, these measures can be considered compensatory measures.\nASSESSMENT OF THE AID MEASURES\nClassification of Odlewnia Śrem’s final product\n(34)\nThe Commission had to verify whether the end product of Odlewnia Śrem belonged to the steel sector as, according to the Communication from the Commission on Rescue and restructuring aid and closure aid for the steel sector‘the Commission considers that rescue aid and restructuring aid for firms in difficulty in the steel sector as defined in Annex B of the multisectoral framework are not compatible with the common market.’\n(35)\nAnnex B to the Multisectoral framework on regional aid for large investment projects (multisectoral framework), which was applicable when the aid was granted, refers to the Combined Nomenclature (CN) code for products which are to be considered steel. These products are listed in two chapters of the CN, namely Chapter 72 (Iron and steel) and chapter 73 (Articles of iron or steel).\n(36)\nAccording to Annex B to the multisectoral framework, the following articles of iron or steel are to be considered steel:\nsheet piling,\nrails and cross ties,\nseamless tubes, pipes and hollow profiles, seamless,\nwelded iron or steel tubes and pipes, the external diameter of which exceeds 406,4 mm,\n(37)\nAccording to the information provided by the Polish authorities, Odlewnia Śrem does not produce any of these products. Moreover, it does not produce any of the products listed in Chapter 72 under the heading ‘Iron and steel’, but uses these products — for example, pig iron — as materials for its own production.\n(38)\nIt produces specific, sophisticated end-products which fall under CN heading 7325, ‘Other cast articles of iron or steel’, and the relevant subheadings such as 7325 10‘Of non-malleable cast iron’ and 7325 99 10‘Of malleable cast iron.’\n(39)\nAnnex B to the multisectoral framework does not classify these articles of iron and steel as steel.\n(40)\nIn conclusion, restructuring aid to Odlewnia Śrem is prima facie not forbidden and the compatibility of such aid must be assessed by the Commission under the applicable 2004 Community Guidelines.\nCompetence of the Commission\n(41)\nAs some of the events relevant to this case took place before the accession of Poland to the European Union on 1 May 2004, the Commission first has to determine whether it is competent to act with regard to the measures in question.\n(42)\nAid measures that were put into effect before accession and are not applicable after accession cannot be examined by the Commission under the -called interim mechanism procedure set out in Annex IV, point 3 of the Accession Treaty or under the procedures laid down in Article 88 of the EC Treaty. Neither the Accession Treaty nor the EC Treaty requires or empowers the Commission to review these measures.\n(43)\nOn the other hand, measures put into effect after accession would constitute new aid and fall within the competence of the Commission under the procedure laid down in Article 88 of the EC Treaty. In order to assess the moment when a certain measure was put into effect, the relevant criterion is the legally binding act by which the competent national authority undertakes to grant aid.\n(44)\nIndividual aid measures are not considered to be applicable after accession if the precise economic exposure of the State was known when the aid was granted.\n(45)\nOn the basis of the information provided by Poland, the Commission was able to identify those measures which were granted before accession and are not applicable thereafter. They are presented in the first part of Table 1 and amount to PLN 19,4 million. It was established that the remaining measures were not granted before accession. Therefore measures worth PLN 24,2 million were considered to have been granted after accession as explained in recital 23 above.\nSTATE AID WITHIN THE MEANING OF ARTICLE 87(1) OF THE EC TREATY\n(46)\nUnder Article 87(1) of the EC Treaty, any aid granted by a Member State or through State resources in any form whatsoever which distorts or threatens to distort competition by favouring certain undertakings or the production of certain goods and affects trade between Member States is incompatible with the common market.\n(47)\nThe notified guarantee, loan, grants, write-offs, deferrals, and arrangements for the payment in instalments of public law liabilities involve the use of state resources. Furthermore, they confer an advantage on the company by reducing its costs. As a company in difficulties, Odlewnia Śrem would not have obtained such financing on similar terms on the market. This advantage consequently distorts competition.\n(48)\nThe state Treasury was ready to forego revenues from taxes and environmental charges due and, by providing subsidies and guarantees, to create an advantage for the company over its competitors. There was no evidence that the Polish authorities acted as a market creditor and the existence of State aid was acknowledged by the Polish authorities in its notification of the aid.\n(49)\nThe beneficiary is active in the cast iron market and exports its products to other EU Member States. The criterion of affecting intra-Community trade is therefore fulfilled.\n(50)\nTherefore the measures which were not granted before accession and constitute new aid were considered State aid within the meaning of Article 87(1) of the EC Treaty. This is not contested by the Polish authorities.\nCompatibility of the aid with the common market: derogation under Article 87(3) of the EC Treaty\n(51)\nThe exemptions in Article 87(2) of the EC Treaty do not apply to the present case. As to the exemptions under Article 87(3) of the EC Treaty, since the primary objective of the aid is to the restore the long-term viability of the undertaking, the only exemption which can be applied is Article 87(3)(c), which allows authorisation of State aid to facilitate the development of certain economic activities where such aid does not adversely affect trading conditions to an extent contrary to the common interest.\nApplicable legal basis\n(52)\nThe Commission assessed the measures constituting new aid and the full restructuring plan in accordance with the applicable rescue and restructuring guidelines. The current Community Guidelines on State aid for rescuing and restructuring firms in difficulty (2004 Guidelines) entered into force on 10 October 2004.\n(53)\nAs already mentioned in the Commission’s decision to initiate the formal investigation procedure, in order to assess the compatibility of the new restructuring aid, the restructuring must be considered as a whole. All the aid measures, not only the new aid, have to be taken into account to establish whether the plan will result in the restoration of viability and whether the aid is limited to the minimum necessary, and to determine the appropriate compensatory measures.\nEligibility of the undertaking\n(54)\nSince Odlewnia Śrem showed a net profit of PLN 3,9 million in 2005, the Commission had doubts as to whether it could be considered a ‘firm in difficulty’ within the meaning of the 2004 Guidelines, and thus be eligible for restructuring aid. These doubts arose in particular because of the lack of information on the beginning of the restructuring period. This meant that the Commission did not know in respect of precisely which point in time the eligibility assessment should be made. Poland has made clear that the restructuring period began in 2003 and Odlewnia Śrem’s net profit of 2005 should therefore be considered a sign of viability being restored during the restructuring.\n(55)\nThe Commission is satisfied that at the beginning of the restructuring in 2003 the company was a firm in difficulty within the meaning of points 9 et seq. of the 2004 Guidelines and is therefore eligible for restructuring aid.\nRestoration of viability\n(56)\nThe 2004 Guidelines state that ‘the restructuring plan, the duration of which must be as short as possible, must restore the long-term viability of the firm within a reasonable timescale and on the basis of realistic assumptions as to future operating conditions. […] The improvement in viability must derive mainly from internal measures […]’.\n(57)\nThe first crucial problem of Odlewnia Śrem was its high level of debt. The Commission notes that the financial restructuring has been completed.\n(58)\nThe company no longer has liquidity problems and all current business liabilities are being repaid on time.\n(59)\nIn its decision to initiate the investigation procedure, the Commission raised doubts as to whether the restructuring was mainly financial and the industrial restructuring aspects were insufficient. In their comments following the decision to initiate the procedure, the Polish authorities have provided sufficient evidence that modernisation of equipment and reorientation of production have been sufficiently addressed.\n(60)\nIn its decision to initiate the procedure the Commission raised doubts concerning the prospects of finding a private investor. However, the company managed to persuade a private company to invest in it, thus increasing its credibility on the market.\n(61)\nMost of the financial analysis indicators show that the company is better off after the restructuring, as its liquidity, solvency and profitability have been enhanced.\n(62)\nOn the basis of these elements, the Commission concludes that its doubts as to whether the plan would lead to restoration of viability have been dispelled.\nAvoidance of undue distortion of competition\n(63)\nThe Commission had doubts as to whether the notified restructuring aid did not unduly distort competition. Poland had to show that the company’s 50 % reduction in its production of cast iron for industrial fittings and termination of its production of cast iron for wind power stations were genuine compensatory measures and not simply the result of external factors such as a decline in demand or inability to compete on the market, and were not therefore necessary to restore viability.\n(64)\nAs Poland has shown, both types of product offer good prospects of profitability. Poland has also shown that Odlewnia Śrem has the technical capacity to produce as much as it did before restructuring. Poland undertakes to limit Odlewnia Śrem’s output of cast iron for industrial fittings to 50 % of its original output and to put a complete stop to its production of cast iron for wind power stations. Hence, the Commission is of the opinion that these measures can be considered a compensatory measure, and not simply actions necessary for the restoration of the company’s viability.\nAid limited to the minimum\n(65)\nThe Polish authorities have provided much detailed information on the amounts considered to be own contributions of the beneficiary to the restructuring costs.\n(66)\nThe Commission is not obliged to take a position on whether the elements listed in recital 31 can be deemed an own contribution to the restructuring, but it considers that the resources listed in recital 30 can be deemed an own contribution.\n(67)\nTo conclude, regarding the sources of financing for restructuring, PLN 23,7 million can be considered a contribution to restructuring from the beneficiary’s own resources or from external resources free of State aid. Total restructuring costs, including those incurred before accession, were PLN 43,6 million. Odlewnia Śrem’s own contribution to overall restructuring costs is therefore 54 %.\n(68)\nThe 2004 Guidelines set the minimum level of the own contribution to restructuring costs at 50 %. The Commission therefore concludes that the own contribution is significant and, in the light of the information provided, the aid is limited to the minimum necessary.\n(69)\nFurthermore, the beneficiary of the aid is based in Stalowa Wola, which is situated in a region eligible for aid under Article 87(3)(a) of the EC Treaty. This is expressly regarded as an additional factor in favour of the compatibility of the aid (see point 56 of the 2004 Guidelines).\nCONCLUSIONS\n(70)\nThe Commission finds that Poland has unlawfully implemented the aid in question in breach of Article 88(3) of the EC Treaty. However, the Commission concludes that the State aid is compatible with the common market,\nHAS ADOPTED THIS DECISION:",
  "extent": "E+W+S+N.I.",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "footnote",
      "label": "f1",
      "text": "OJ L 83, 27.3.1999, p. 1."
    },
    {
      "type": "footnote",
      "label": "f2",
      "text": "OJ C 244, 1.10.2004, p. 2."
    },
    {
      "type": "footnote",
      "label": "f3",
      "text": "OJ C 70, 19.3.2002, p. 21."
    },
    {
      "type": "footnote",
      "label": "f4",
      "text": "OJ C 70, 19.3.2002, p. 8."
    },
    {
      "type": "footnote",
      "label": "f5",
      "text": "OJ L 279, 23.10.2001, p. 1."
    },
    {
      "type": "footnote",
      "label": "f6",
      "text": "Judgment of the Court of First Instance in Case T-109/01 Fleuren Compost v Commission [2004] ECR II-127, paragraph 74."
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/eudn/2009/523/introduction",
    "retrieved_at": "2026-11-01T15:16:27.335419+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}