# Commission Implementing Decision of 28 February 2012 establishing the best available techniques (BAT) conclusions under Directive 2010/75/EU of the European Parliament and of the Council on industrial emissions for the manufacture of glass (notified under document C(2012) 865) (Text with EEA relevance) (2012/134/EU), Division: DEFINITIONS

Extent: E+W+S+N.I.

For the purposes of these BAT conclusions, the following definitions apply:
Term used
Definition
New plant
A plant introduced on the site of the installation following the publication of these BAT conclusions or a complete replacement of a plant on the existing foundations of the installation following the publication of these BAT conclusions
Existing plant
A plant which is not a new plant
New furnace
A furnace introduced on the site of the installation following the publication of these BAT conclusions or a complete rebuild of a furnace following the publication of these BAT conclusions
Normal furnace rebuild
A rebuild between campaigns without a significant change in furnace requirements or technology and in which the furnace frame is not significantly adjusted and the furnace dimensions remain basically unchanged. The refractory of the furnace and, where appropriate, the regenerators are repaired by the full or partial replacement of the material.
Complete furnace rebuild
A rebuild involving a major change in the furnace requirements or technology and with major adjustment or replacement of the furnace and associated equipments.

---
Source: https://www.legislation.gov.uk/eudn/2012/134/annex/division/2 (the official version)
Page: https://openlegislation.uk/eu-decision-2012-134/annex/division-2