Article 5
United Kingdom
1.
Italyshall recover from SACE BT the incompatible aid such as defined in Articles 2, 3 and 4.
2.
The sums to be recovered shall bear interest from the date on which they were put at the disposal of SACE BT until their actual recovery, namely: EUR 156 000 as of 5 June 2009 (Article 2), EUR 29 million as of 18 June 2009 (Article 3) and EUR 41 million as of 4 August 2009 (Article 4).
3.
The interest shall be calculated on a compound basis in accordance with Chapter V of Regulation (EC) No 794/2004f1.
4.
Recovery of the aid shall be immediate and effective.
5.