  "url": "https://openlegislation.uk/eu-decision-2014-713/article-1",
  "json_url": "https://openlegislation.uk/eu-decision-2014-713/article-1.json",
  "legislation": "eudn/2014/713",
  "legislation_title": "Commission Decision of 13 October 2014 on the establishment of the annual priority lists for the development of network codes and guidelines for 2015 (Text with EEA relevance) (2014/713/EU)",
  "legislation_url": "https://openlegislation.uk/eu-decision-2014-713",
  "path": "article/1",
  "kind": "article",
  "number": "1",
  "heading": null,
  "text": "The Commission establishes for the development of harmonised electricity rules this annual priority list for 2015:\nnetwork connection rules:\nrules on requirements for grid connection applicable to generators (Commission adoption phase),\ndemand connection (Commission adoption phase),\nrules on high-voltage direct current transmission system connection (finalise network code and start Commission adoption phase),\nsystem operation rules:\nrules on load-frequency control and reserves (Commission adoption phase),\nrules on emergency requirements & procedures (finalise network code and start Commission adoption phase),\nrules on operational security (Commission adoption phase),\nrules on operational planning and scheduling (Commission adoption phase),\nrules on capacity allocation and congestion management for day-ahead and intraday markets, including capacity calculation (Commission adoption phase),\nbalancing rules including network-related reserve power (finalise network code and start Commission adoption phase),\nrules for longer term (forward) capacity allocation (Commission adoption phase),\nrules regarding harmonised transmission tariff structures (scoping by ACER to prepare framework guideline).",
  "extent": "E+W+S+N.I.",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "footnote",
      "label": "f1",
      "text": "Regarding rules on investment incentives, the TEN-E Regulation, notably Article 13, provides for rules to ensure that appropriate incentives are granted to infrastructure projects of common interest in gas and electricity. In this context, the TEN-E Regulation sets out the following tasks: each national regulatory authority to submit to ACER its methodology and criteria used to evaluate investments and the higher risks incurred by them, where available, by 31 July 2013, ACER to facilitate the sharing of good practices and to make recommendations by 31 December 2013, each national regulatory authority to publish its respective methodology and the criteria used to evaluate investments and the higher risks incurred by them by 31 March 2014. Based on the input from the abovementioned tasks, the European Commission will decide whether guidelines need to be issued."
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/eudn/2014/713/article/1",
    "retrieved_at": "2026-11-01T15:14:37.657536+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}