Article 2
United Kingdom
The annual priority list for 2016 for the development of harmonised electricity rules shall be the following:
-
network connection rules:
-
rules on requirements for grid connection applicable to generators (Commission continuing adoption phase after Committee voting in 2015),
-
demand connection (Commission continuing adoption phase after Committee voting in 2015),
-
rules on high-voltage direct current transmission system connection (Commission continuing adoption phase after Committee voting in 2015),
-
-
rules regarding system operations (Commission continuing adoption phase after Committee voting in 2015),
-
rules for longer term (forward) capacity allocation (Commission continuing adoption phase after Committee voting in 2015),
-
balancing rules including network-related reserve power (finalise network code and start Commission adoption phase),
-
rules on emergency & restoration (finalise network code and start Commission adoption phase),
-
rules regarding harmonised transmission tariff structures (ACER to prepare framework guideline depending on the results of ACER's scoping activity and decisions taken as part of the energy market design initiative).