Division BAT 1 In order to improve the overall environmental performance, BAT is to implement and adhere to an environmental management system (EMS) that incorporates all of the following features:
United Kingdom
- I..
commitment of the management, including senior management;
- II..
definition of an environmental policy that includes the continuous improvement of the installation by the management;
- III..
planning and establishing the necessary procedures, objectives and targets, in conjunction with financial planning and investment;
- IV..
implementation of procedures paying particular attention to:
- (a)
structure and responsibility
- (b)
recruitment, training, awareness and competence
- (c)
communication
- (d)
employee involvement
- (e)
documentation
- (f)
effective process control
- (g)
maintenance programmes
- (h)
emergency preparedness and response
- (i)
safeguarding compliance with environmental legislation;
- (a)
- V..
checking performance and taking corrective action, paying particular attention to:
- (a)
monitoring and measurement (see also the Reference Report on Monitoring)
- (b)
corrective and preventive action
- (c)
maintenance of records
- (d)
independent (where practicable) internal and external auditing in order to determine whether or not the EMS conforms to planned arrangements and has been properly implemented and maintained;
- (a)
- VI..
review of the EMS and its continuing suitability, adequacy and effectiveness by senior management;
- VII..
following the development of cleaner technologies;
- VIII..
consideration for the environmental impacts from the eventual decommissioning of the installation at the stage of designing a new plant, and throughout its operating life;
- IX..
application of sectoral benchmarking on a regular basis.
In some cases, the following features are part of the EMS:
- X..
waste management plan (see BAT 11);
- XI..
quality control plan for recovered wood used as raw material for panels and used as a fuel (see BAT 2b);
- XII..
noise management plan (see BAT 4);
- XIII..
odour management plan (see BAT 9);
- XIV..
dust management plan (see BAT 23).