The arbitrators shall base the timetable adopted under paragraph 7.a. on the following:

a.Receipt of written submissions of the Parties to the arbitration:

(1)

Requesting Party:

- - - - - - - - - - 2 weeks

(2)

Responding Party:

- - - - - - - - - - 2 weeks
b.Receipt of third party submissions:- - - - - - - - - - 1 week
c.Substantive meeting with the arbitrators:- - - - - - - - - - 1-2 weeks
d.Responses to questions to Parties and third Parties to the arbitration:- - - - - - - - - - 1-2 weeks
e.Issuance and circulation of the arbitrators' report on its determination:- - - - - - - - - - 4 weeks

Consistent with the provisions of paragraph 11., the arbitrators may change the above timetable and may schedule additional meetings with the Parties to the arbitration after consulting them.