Article 2 Actions and timetable
United Kingdom
Estonia, Latvia, Lithuania and Poland shall ensure the timely implementation of the following actions:
- (a)
by 31 December 2018:
- (1)
consolidated preliminary technical design shall be completed in Estonia, Latvia and Lithuania;
- (2)
strategic environmental assessments shall be completed in Estonia, Latvia and Lithuania (except from Kaunas to Vilnius and from Kaunas to Lithuania/Poland state border);
- (3)
the study on infrastructure management in Estonia, Latvia and Lithuania shall be completed and submitted to the national authorities of Estonia, Latvia and Lithuania;
- (1)
- (b)
by 30 June 2019: a decision on the management of the built infrastructure shall be concluded by Estonia, Latvia and Lithuania;
- (c)
by 31 December 2020:
- (1)
strategic environmental assessments shall be completed in Lithuania from Kaunas to Lithuania/Poland state border;
- (2)
the spatial (territorial) planning shall be completed and the detailed route alignment approved in Estonia, Latvia and Lithuania (except from Kaunas to Vilnius);
- (3)
construction shall have been started in Estonia, Latvia and Lithuania;
- (4)
the technical design of the railway shall be completed in Estonia, Latvia (central section around Riga) and Lithuania (except from Kaunas to Vilnius and from Kaunas to Lithuania/Poland state border);
- (5)
detailed studies and environmental procedures defining the technical parameters and timeframe for the implementation of the section Ełk-Poland/Lithuania state border shall be completed in Poland;
- (1)
- (d)
by 31 December 2021:
- (1)
the land acquisition shall be completed in Estonia, Latvia and Lithuania (except from Kaunas to Vilnius and from Kaunas to Lithuania/Poland state border);
- (2)
the spatial (territorial) planning and strategic environmental assessments shall be completed and the detailed route alignment approved in Lithuania from Kaunas to Vilnius;
- (3)
the technical design shall be completed in Latvia (northern and southern sections);
- (1)
- (e)
by 31 December 2023:
- (1)
the land acquisition shall be completed in Lithuania from Kaunas to Vilnius and from Kaunas to Lithuania/Poland state border;
- (2)
the technical design of the railway shall be completed in Lithuania from Kaunas to Lithuania/Poland state border and from Kaunas to Vilnius;
- (1)
- (f)
by 31 December 2025:
- (1)
the railway infrastructure shall be completed as a double-track railway line for mixed traffic, suitable for minimum 740-m long freight trains, electrified, in UIC gauge, in Estonia, Latvia, Lithuania and Poland;
- (2)
the European Rail Traffic Management System (ERTMS) shall be deployed to achieve the full interoperability, in accordance with Commission Implementing Regulation (EU) 2017/6f1, in Estonia, Latvia, Lithuania and Poland;
- (3)
capacity shall be ensured for the trans-shipment in existing and new rail-road terminals, which shall be connected by a fast conventional double track electrified railway line and European standard gauge (1 435 mm).
- (1)