UNOPS will be responsible for the technical implementation of the project.

  1. Activity 1: Increasing the number of UNVIM personnel.
  2. Activity 2: Renting of a part of the Djibouti port and renting of an office in Sanaa. The Union will continue to fund the rental of the port facilities to ensure a constant location at which to conduct inspections. In addition, the Union will finance the rental of the Sanaa office, which serves as a temporary base for UNVIM staff to connect from and to Hodeidah and Djibouti.
  3. Activity 3: Purchasing additional inspection equipment. UNVIM will purchase additional inspection equipment (such as scanners) necessary for the implementation of the EU Stabilisation Action. It will facilitate the timely inspection of vessels in Djibouti port and in international waters.
  4. Activity 4: Upgrading UNVIM’s security. This activity will be dedicated to ensuring that UNVIM’s operations in the ports of the Red Sea meet the appropriate security requirements and allow for UNVIM’s work to be properly conducted.
  5. Activity 5: Project implementation. UNOPS will provide programme management oversight. This oversight is to include the development of milestones, internal reviews, oversight of contractual agreements and financial management. Anticipated activities include: