OpenLegislation

Division 2.2.2 Destructive testingF1

United Kingdom

Original text. Later amendments are not shown.

Destructive testing shall be carried out in accordance with the single sampling plan below and shall be used only for batches of 100 or more.

The number of prepackages checked shall be equal to 20.

  • If the number of defective units found in the sample is less than or equal to the acceptance criterion, the batch of prepackages shall be considered as acceptable.

  • If the number of defective units found in the sample is equal to or greater than the rejection criterion, the batch of prepackages shall be rejected.

Number in batch Number in sample Number of defective units
Acceptance criterion Rejection criterion
Whatever the number (≥ 100) 20 1 2

Annotations

Textual amendments

F1

Substituted by Commission Directive of 28 September 1978 adapting to technical progress the Annexes to Council Directives 75/106/EEC and 76/211/EEC on prepackaging (78/891/EEC).