# Council Directive 92/57/EEC of 24 June 1992 on the implementation of minimum safety and health requirements at temporary or mobile constructions sites (eighth individual Directive within the meaning of Article 16 (1) of Directive 89/391/EEC), Article 4: Project preparation stage: general principles

Extent: E+W+S+N.I.

The project supervisor, or where appropriate the client, shall take account of the general principles of prevention concerning safety and health referred to in Directive 89/391/EEC during the various stages of designing and preparing the project, in particular:
when architectural, technical and/or organizational aspects are being decided, in order to plan the various items or stages of work which are to take place simultaneously or in succession,
when estimating the period required for completing such work or work stages. Account shall also be taken, each time this appears necessary, of all safety and health plans and of files drawn up in accordance with Article 5 (b) or (c) or adjusted in accordance with Article 6 (c).

---
Source: https://www.legislation.gov.uk/eudr/1992/57/article/4 (the official version)
Page: https://openlegislation.uk/eu-directive-1992-57/article-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.