Division 1
United Kingdom
Facilities
- (a)
A hatchery must be physically and operationally separate from rearing facilities. The layout must be such as to allow the various functional units listed below to be kept separate:
-
egg storage and grading,
-
disinfection,
-
pre-incubation,
-
hatching,
-
preparation and packaging of goods for dispatch,
-
- (b)
Buildings must be protected against birds coming from outside and rodents; floors and walls must be of hard-wearing, impervious and washable materials; natural or artificial lighting and air flow and temperature systems must be of an appropriate type; provision must be made for the hygienic evacuation of waste (eggs and chicks).
- (c)
Equipment must have smooth and waterproof surfaces.