The total emission limit values in the table below refer to all process stages carried out at the same installation from electrophoretic coating, or any other kind of coating process, through to the final wax and polish of topcoating inclusive, as well as solvent used in cleaning of process equipment, including spray booths and other fixed equipment, both during and outside of production time.

Activity(solvent consumption threshold in tonnes/year)Production threshold(refers to annual production of coated item)Total emission limit value
New installationsExisting installations
Coating of new cars (> 15)> 5 00045 g/m2 or 1,3 kg/body + 33 g/m2 60 g/m2 or 1,9 kg/body + 41 g/m2
≤ 5 000 monocoque or > 3 500 chassis-built90 g/m2 or 1,5 kg/body + 70 g/m2 90 g/m2 or 1,5 kg/body + 70 g/m2
Total emission limit value (g/m2)
Coating of new truck cabins (> 15)≤ 5 0006585
> 5 0005575
Coating of new vans and trucks (> 15)≤ 2 50090120
> 2 5007090
Coating of new buses (> 15)≤ 2 000210290
> 2 000150225