  1. (a)

    Member States shall take measures to ensure that:

    1. (i)

      the guarantee of origin of the electricity produced from high-efficiency cogeneration:

      • enable producers to demonstrate that the electricity they sell is produced from high-efficiency cogeneration and is issued to this effect in response to a request from the producer,

      • is accurate, reliable and fraud-resistant,

      • is issued, transferred and cancelled electronically;

    2. (ii)

      the same unit of energy from high-efficiency cogeneration is taken into account only once.

  2. (b)

    The guarantee of origin referred to in Article 14(10) shall contain at least the following information:

    1. (i)

      the identity, location, type and capacity (thermal and electrical) of the installation where the energy was produced;

    2. (ii)

      the dates and places of production;

    3. (iii)

      the lower calorific value of the fuel source from which the electricity was produced;

    4. (iv)

      the quantity and the use of the heat generated together with the electricity;

    5. (v)

      the quantity of electricity from high-efficiency cogeneration in accordance with Annex II that the guarantee represents;

    6. (vi)

      the primary energy savings calculated in accordance with Annex II based on the harmonised efficiency reference values indicated in point (f) of Annex II;

    7. (vii)

      the nominal electric and thermal efficiency of the plant;

    8. (viii)

      whether and to what extent the installation has benefited from investment support;

    9. (ix)

      whether and to what extent the unit of energy has benefited in any other way from a national support scheme, and the type of support scheme;

    10. (x)

      the date on which the installation became operational; and

    11. (xi)

      the date and country of issue and a unique identification number.

    The guarantee of origin shall be of the standard size of 1 MWh. It shall relate to the net electricity output measured at the station boundary and exported to the grid.