Division (16) As regards the capacity restrictions of a duration of at least 30 consecutive days and affecting more than 50 % of the estimated traffic volume on a railway line, the infrastructure manager shall provide the applicants upon their request during the first round of consultation with a comparison of the conditions to be encountered under at least two alternatives of capacity restrictions. The infrastructure manager shall design those alternatives on the basis of the input provided by the applicants at the time of their requests and jointly with them.F1

United Kingdom

Original text. Later amendments are not shown.

The comparison shall, for each alternative, include at least:

  1. (a)

    the duration of the capacity restriction,

  2. (b)

    the expected indicative infrastructure charges due,

  3. (c)

    the capacity available on diversionary lines,

  4. (d)

    the available alternative routes, and

  5. (e)

    the indicative travel times.

Before making a choice between the alternatives of capacity restrictions, the infrastructure manager shall consult the interested applicants and take into account the impacts of the different alternatives on those applicants and on the users of the services.

Annotations

Textual amendments

F1

Substituted by Commission Delegated Decision (EU) 2017/2075 of 4 September 2017 replacing Annex VII to Directive 2012/34/EU of the European Parliament and of the Council establishing a single European railway area (Text with EEA relevance).