Article 10
United Kingdom
The supplier shall perform his obligations in accordance with the conditions laid down in the tender notice as well as his responsibilities under this Regulation, including those arising from his tender.
The supplier shall be deemed to be acquainted with all applicable general and special conditions and to have accepted them.
In order to ensure that he meets his obligations, the supplier shall lodge a delivery guarantee with the Commission within 10 working days of notification of the award of the contract. That guarantee, expressed in ecus, shall represent 10 % of the amount of the tender per lot. The period of validity shall be at least one year and shall be extended on request of the Commission. It shall be lodged in accordance with the second and third paragraphs of Article 8. It must expressly state that is has been lodged in accordance with this Article and must include the particulars referred to in points (a) and (b) of Article 7 (3). It shall also indicate the country or organization receiving the aid.
Within 10 working days of notification of the award of the contract, the supplier shall inform in writing the enterprise referred to in Article 11 of:
the name and address of the manufacturer, packer or stockholder of the goods to be delivered, and the approximate date of manufacture or packaging.
Where the mobilization concerns a processed product, the supplier shall, at least three working days in advance, communicate the date when the manufacturing or the packaging process begins;
the name of his representative at the place of delivery.
The rights and obligations entailed by the award of the contract shall not be transferable.