Article 16
United Kingdom
The monitor shall check the quality, quantity, packing and marking of the goods to be delivered in respect of each supply.
The final check shall be carried out at the delivery stage specified. In the case of delivery free at port of landing or free at destination, a provisional check shall also be carried out when the goods are loaded or at the factory.
The check shall be carried out at a time and under conditions which make it possible to obtain all the results of analyses required and, where appropriate, the results of a second inspection, before the goods are made available, or before the commencement of loading. However, in special circumstances, particularly where there is a risk of product substitution taking place in the course of supply after the said checks, the monitor may, after authorization by the Commission, make additional checks of the same kind during the loading operations. Any financial costs arising from the discovery of non-conformity during these latter checks, in particular any demurrage costs, shall be borne by the supplier.
When the final check is complete, the monitor shall issue the supplier with a final certificate of conformity specifying in particular the date of completion of the supply and the net quantity supplied; such certificate shall be subject to reservations if necessary.
Where the monitor establishes a non-conformity, he must notify the supplier and the Commission in writing as soon as possible. This shall be known as the ‘notice of reservation’. If the supplier wishes to dispute the findings with the monitor and the Commission, he must do so within two working days of dispatch of this notice.
When the provisional check is complete, the monitor shall issue the supplier a provisional certificate of conformity subject to reservation if necessary. The monitor shall state whether the reservation is such as to render the goods unacceptable at the delivery stage. In the light of any reservations, the Commission may decide not to pay the advance referred to in Article 18 (4).
The supplier shall bear an financial consequences, including dead freight costs and demurrage, in the event of qualitative shortcomings or late presentation of the goods for checking.
The monitor shall issue written invitations to the representatives of the supplier and of the beneficiary to be present at the checking operations, in particular the taking of samples to be used for analyses. The taking of samples shall be carried out in accordance with professional practice.
When sampling is undertaken, the monitor shall take two additional samples which he shall keep under seal at the Commission's disposal for the purpose of any second check or in the event of objections being raised by the beneficiary or supplier.
The cost of the goods taken as samples shall be borne by the supplier.
If the supplier or the beneficiary objects to the findings of a provisional or final check carried out in accordance with paragraph 2, the monitor, after authorization of the Commission, shall arrange for a second inspection involving, according to the nature of the objection, a second sampling, second analysis, a reweighing or rechecking of the packaging.
The second inspection shall be carried out by an agency or laboratory designated by agreement between the supplier, the beneficiary and the monitor. If it proves impossible for agreement to be reached on this point within two working days of the notification of the objection, the Commission shall automatically appoint an agency or laboratory for the purpose.
If the final certificate of conformity is not issued after the first checks or second inspection have been carried out, the supplier shall be obliged to replace the goods.
The costs relating to the checks referred to in paragraph 2 shall be borne by the Commission.
The cost of checking the replacement or additional goods referred to in paragraph 9 and Article 17 (1) shall be borne by the supplier.
The costs of the second inspection referred to in paragraph 8 shall be borne by the losing party.
In the event of disruptions which severely impede a supply of goods free at port of landing or free at destination for reasons which are not attributable to the supplier, the Commission may decide that the monitor shall issue a final certificate of conformity before the supply has been carried out, on the basis of an appropriate check on the quantity and quality of the goods.
The supplier may ask the monitor to issue a provisional or final certificate of conformity in respect of part of the consignment.
However, no more than three part-certificates may be issued in respect of a single lot. A part-certificate may not be issued in respect of less than 2 500 tonnes net of unprocessed cereals and 100 tonnes net of other goods, except where it relates to the balance of a given lot. In all these cases, the Commission shall require the supplier to bear the additional checking costs. However, the last-mentioned provision shall not apply in the case of a lot divided in sublots each having a different destination.